Industry guide · Saudi Arabia

Green hydrogen and ammonia in Saudi Arabia: oxygen and moisture measurement

NEOM's green hydrogen plant has finished construction and is being commissioned for 2027. This guide shows where oxygen and water are measured from the electrolyser to the ammonia loop.

The project

Saudi Arabia's first large green hydrogen plant, built by NEOM Green Hydrogen Company (an equal joint venture of ACWA Power, Air Products and NEOM), finished construction in August 2026 and is now being commissioned, with commercial operation targeted for 2027. The plant converts renewable power into hydrogen and then into green ammonia for export.

600 t/dayhydrogen, at full output
≈ 4 GWsolar and wind power for the electrolysers
2027commercial operation targeted
1.2 Mt/yrrenewable ammonia marketed by Yara (up to)

Figures as reported by ACWA Power and in the trade press (see References). Air Products holds a 30-year offtake for the ammonia.

Where oxygen and moisture are measured

Green ammonia is made in three steps: electrolysis makes hydrogen, an air separation unit makes nitrogen, and the ammonia loop combines them. Oxygen and water are the impurities that matter most along the way: oxygen is a safety issue in the electrolyser, and both are poisons for the ammonia synthesis catalyst.

#PointMeasuresTypical limitSuggested YORK instrument
1Raw hydrogen before the deoxo reactorO₂ in H₂ (%)About 0.15–0.3 mol % from alkaline electrolysers (design study)PGA500-EX
2Oxygen side of the electrolyserH₂ in O₂Alarm and trip levels from the electrolyser safety conceptIntegrated system: thermal-conductivity H₂-in-O₂ analyzer
3After deoxo and dryerTrace O₂ and trace waterSet by the downstream use; for fuel-cell hydrogen ≤ 5 µmol/mol each (ISO 14687 Grade D)PGA500-EX, DPT990-EX
4Nitrogen from the air separation unitTrace O₂ and water in N₂Set by the ammonia catalyst licensorPGA500, DPT830
5Synthesis make-up gas (H₂ + N₂)Trace water and oxygenCatalyst poisons: limits from the licensor specificationDPT990-EX, PGA500-EX
6Field checksPortable dew point checksVerify online analyzersDPT-600 Plus-EX (portable, hazardous area)

Getting reliable readings

  • Hazardous areas. Electrolyser halls, hydrogen compression and the ammonia loop are classified areas: use explosion-proof analyzers or a certified analyzer shelter. Certificate details are sent with quotations.
  • Sensor life in hydrogen. Hydrogen shortens the life of electrochemical oxygen sensors to about 12 months: plan regular sensor replacement.
  • Pressure. Reduce the sample to near-atmospheric pressure (the dew point analyzers accept up to 4 barg) and use the instrument's conversion to report line-pressure dew point.
  • Specifications. The catalyst licensor and the offtake contract set the exact limits; the values here are typical published figures.

Frequently asked questions

When does the NEOM green hydrogen plant start production?

Construction finished in August 2026 and the plant is being commissioned. ACWA Power has said commercial operation is targeted for 2027.

Why measure oxygen in electrolytic hydrogen?

Raw hydrogen from an alkaline electrolyser can carry about 0.15–0.3 mol % oxygen. The reading controls the deoxo reactor and detects crossover, which is a safety issue.

Why do water and oxygen matter for green ammonia?

Both poison the ammonia synthesis catalyst, so the nitrogen and the make-up gas are dried and deoxygenated. The catalyst licensor sets the exact limits.

Which YORK analyzers suit hydrogen areas?

The explosion-proof DPT990-EX (dew point) and PGA500-EX (trace oxygen) for in-line points, and the intrinsically safe DPT-600 Plus-EX for portable dew point checks. Certificate details are sent with quotations.